Reconstruction of ZCB Ekoklinkier- photo - reportage
Tuesday, 2008-02-26
At the moment, the overhaul of the bricks storage area (store) has been already finished as a result of favourable weather conditions and intensive reconstruction works are carried out in production shop in the bricks forming plant destroyed in the fire occurred last year. After the reconstruction of production shop, the assembling of the new machines in forming plant and the modernization of bricks firing plant – tunnel kiln in Building Ceramic Facility is planned. The photos documenting the progress of works are included below.. |
The assembling of elements of the new structure in production shop 14-02-2008. ![]() |
The assembling of wall heating of the new structure in production shop 18-02-2008. ![]() |
The assembling of roofing of the new structure in production shop 21-02-2008. ![]() |
Completed production shop 25-02-2008. ![]() |
Next photos will be published soon |